EARTHWORK QUANTITIES
EARTH QUANTITIES GENERATED FROM SPOT ELEVATIONS PROJECT SUMMARY & OUR ROLE: Our client provided elevations and slopes on the plan and would to get earthwork quantities and how much grading construction costs. OUR ROLE: + We created the proposed surface to generate earthwork numbers, cross-sections, earthwork analysis. + To get earthwork more true factor, we […]
EARTH QUANTITIES GENERATED FROM SPOT ELEVATIONS
- PROJECT SUMMARY & OUR ROLE:
Our client provided elevations and slopes on the plan and would to get earthwork quantities and how much grading construction costs.
- OUR ROLE:
+ We created the proposed surface to generate earthwork numbers, cross-sections, earthwork analysis.
+ To get earthwork more true factor, we had to subtract 1 foot on parking stalls and driveway area and also used 10 percent shrinkage in cut, so it takes 1.10 cubic yard of dirt to fill 1 cubic yard of dirt.